Handover and Construction Progress
Phase 12 of Nad Al Sheba Gardens is due for handover in June 2030 and is not yet on the Dubai Land Department's register. Of the earlier phases, one is finished and Phase 3 is at 97.03%; Phase 2 finished a year after its planned date.
Phase 12's handover is June 2030 by Meraas's payment plan, which its broker Homes.me publishes. No work on it can be measured yet: the phase was not on the Dubai Land Department's project register when Offplan.tv read it on Nov 11, 2026. Everything below is the earlier phases, which show how this developer's dates have held in this community.
Every phase on the register, read Nov 11, 2026
| Phase | Built, per the register | Status | Planned end on the register | Developer's own date |
|---|---|---|---|---|
| Phase 2 | 100% | Finished Dec 17, 2025 | Dec 1, 2024 | |
| Phase 3 | 97.03% | Under construction | Apr 19, 2026 | |
| Phase 4 | 76.3% | Under construction | Not given | First quarter of 2027 (Dubai Holding) |
| Phase 5 | 37.53% | Under construction | Not given | |
| Phase 6 | 13.85% | Under construction | Not given | |
| Phase 7 | 4.01% | Under construction | Feb 15, 2028 | Second quarter of 2028 (Dubai Holding) |
| Phases 8 and 9 | 0.7% | Under construction | Oct 1, 2028 | |
| Phase 10 | 0.35% | Not started | Oct 1, 2028 | |
| Phase 11 | 0.06% | Not started | Jul 1, 2029 | |
| Phase 12 | Not on the register | June 2030 (payment plan) |
The percentages are the land department's, not Meraas's, and the register's figure can trail the site by weeks. Each phase name links to its page on Offplan.tv, which shows the register entry.
What the record shows
Two phases have reached or passed their registered end dates, and both ran late. Phase 2 was planned for Dec 1, 2024 and is recorded as finished on Dec 17, 2025, a little over twelve months on. Phase 3 was planned for Apr 19, 2026 and was still short of complete, at 97.03%, almost seven months later.
Phase 7 shows the gap between a sale and a building contract. Its register entry starts on Jan 28, 2025; Meraas awarded the construction contract, worth almost AED 1 billion, on Sep 24, 2026, twenty months later, and the register showed 4.01% built seven weeks after that. Dubai Holding's completion date for it, the second quarter of 2028, is already later than the register's Feb 15, 2028.
Phase 12 is one row of 29 villas, a far smaller job than Phase 7's 272 homes, and its June 2030 date allows about three and a half years. We think that is enough time on paper, and that the date still slips by a few months, because the two phases with a finished record both did.
Confidence: Possible. Check by: Sep 2030.
The site, in Meraas's films
Meraas's June 2026 progress film looks down on streets of finished villas, with the last external works still under way between them. The film covers Phases 3 and 4 and does not label its shots.
By the third quarter of 2026 Phase 4's rows of homes stand as finished structures across the site, with cranes still among them.
The film for Phases 5 and 6 from the same quarter shows villas wrapped in scaffolding with finishing work going on. Meraas does not label which shots are which phase.
Later in the same film the villas are bare concrete frames, the earlier stage that matches the register's lower figure for Phase 6.
What a finished villa looks like
In November 2025, a month before the register recorded Phase 2 as finished, Meraas filmed inside a completed villa: a freestanding bath against veined stone, then a skylit stair hall. It is the only footage of a built home in the community that Meraas has published, and the nearest thing to evidence of the finish Phase 12 buyers are promised.
Sources
- Nad Al Sheba Gardens Phase 12, Homes.me, publishing Meraas's Phase 12 payment plan of November 2026; read Nov 12, 2026
- Offplan.tv's pages for Phase 2, Phase 3, Phase 4, Phase 5, Phase 6, Phase 7, Phases 8 and 9, Phase 10 and Phase 11, from the Dubai Land Department's project register read Nov 11, 2026; opened Nov 12, 2026
- Meraas awards contract valued at over AED 690 million for new phase of Nad Al Sheba Gardens, Dubai Holding, May 21, 2025
- Meraas awards AED 1 billion contract for Phase 7 of Nad Al Sheba Gardens, Dubai Holding, Sep 24, 2026
Moments
Site Progress June 2026 | Nad Al Sheba Gardens - Phase 3-4
Meraas
Site Progress Q3 2026 | Nad Al Sheba Gardens 4
Meraas
Site Progress Q3 2026 | Nad Al Sheba Gardens 5 & 6
Meraas
Nad Al Sheba Gardens | First look inside
Meraas
See also
-
All Phases ComparedNad Al Sheba Gardens has nine phase entries on the Dubai Land Department's register, Phases 2 to 11, holding about 1,778 homes. Phase 12 adds 29 villas, the smallest release by far, the only one with no townhouses and the first to start above AED 13M. -
Location and Drive TimesNad Al Sheba Gardens is in Nad Al Sheba 1, Dubai, beside Meydan. Meraas's Phase 12 briefing says 10 minutes to Downtown Dubai and 15 to the airport; Vi.ki's own routing check on Nov 12, 2026 gave about 21 and 26 minutes with no traffic, over 15 and 22 km of road. -
Masterplan and AmenitiesPhase 12 sits in one row along the northern edge of Nad Al Sheba Gardens, above a linear park, and Meraas draws four amenities for it, a beach pool, a community pool, open gardens and a gym. The wider community is planned around a lagoon chain, a wave pool, a mall and a school. - Resale Prices and Registered SalesThe Dubai Land Department has 960 registered off-plan sales in Nad Al Sheba Gardens Phases 2 to 11, worth about AED 5.03 billion. Phase 11's median was AED 3,141 per sq ft, above Phase 12's starting AED 2,743 to 2,857. Meraas's 49% resale claim is the seller's.