Handover and Construction Progress

Phase 12 of Nad Al Sheba Gardens is due for handover in June 2030 and is not yet on the Dubai Land Department's register. Of the earlier phases, one is finished and Phase 3 is at 97.03%; Phase 2 finished a year after its planned date.

Phase 12's handover is June 2030 by Meraas's payment plan, which its broker Homes.me publishes. No work on it can be measured yet: the phase was not on the Dubai Land Department's project register when Offplan.tv read it on Nov 11, 2026. Everything below is the earlier phases, which show how this developer's dates have held in this community.

Every phase on the register, read Nov 11, 2026

Phase Built, per the register Status Planned end on the register Developer's own date
Phase 2 100% Finished Dec 17, 2025 Dec 1, 2024
Phase 3 97.03% Under construction Apr 19, 2026
Phase 4 76.3% Under construction Not given First quarter of 2027 (Dubai Holding)
Phase 5 37.53% Under construction Not given
Phase 6 13.85% Under construction Not given
Phase 7 4.01% Under construction Feb 15, 2028 Second quarter of 2028 (Dubai Holding)
Phases 8 and 9 0.7% Under construction Oct 1, 2028
Phase 10 0.35% Not started Oct 1, 2028
Phase 11 0.06% Not started Jul 1, 2029
Phase 12 Not on the register June 2030 (payment plan)

The percentages are the land department's, not Meraas's, and the register's figure can trail the site by weeks. Each phase name links to its page on Offplan.tv, which shows the register entry.

What the record shows

Two phases have reached or passed their registered end dates, and both ran late. Phase 2 was planned for Dec 1, 2024 and is recorded as finished on Dec 17, 2025, a little over twelve months on. Phase 3 was planned for Apr 19, 2026 and was still short of complete, at 97.03%, almost seven months later.

Phase 7 shows the gap between a sale and a building contract. Its register entry starts on Jan 28, 2025; Meraas awarded the construction contract, worth almost AED 1 billion, on Sep 24, 2026, twenty months later, and the register showed 4.01% built seven weeks after that. Dubai Holding's completion date for it, the second quarter of 2028, is already later than the register's Feb 15, 2028.

Phase 12 is one row of 29 villas, a far smaller job than Phase 7's 272 homes, and its June 2030 date allows about three and a half years. We think that is enough time on paper, and that the date still slips by a few months, because the two phases with a finished record both did.

Confidence: Possible. Check by: Sep 2030.

The site, in Meraas's films

Meraas's June 2026 progress film looks down on streets of finished villas, with the last external works still under way between them. The film covers Phases 3 and 4 and does not label its shots.

By the third quarter of 2026 Phase 4's rows of homes stand as finished structures across the site, with cranes still among them.

The film for Phases 5 and 6 from the same quarter shows villas wrapped in scaffolding with finishing work going on. Meraas does not label which shots are which phase.

Later in the same film the villas are bare concrete frames, the earlier stage that matches the register's lower figure for Phase 6.

What a finished villa looks like

In November 2025, a month before the register recorded Phase 2 as finished, Meraas filmed inside a completed villa: a freestanding bath against veined stone, then a skylit stair hall. It is the only footage of a built home in the community that Meraas has published, and the nearest thing to evidence of the finish Phase 12 buyers are promised.

Sources

Moments

Site Progress June 2026 | Nad Al Sheba Gardens - Phase 3-4

Meraas

  1. Meraas's June 2026 progress film looks down on streets of finished villas, with the last external works still under…

Site Progress Q3 2026 | Nad Al Sheba Gardens 4

Meraas

  1. By the third quarter of 2026 Phase 4's rows of homes stand as finished structures across the site, with cranes still…

Site Progress Q3 2026 | Nad Al Sheba Gardens 5 & 6

Meraas

  1. The film for Phases 5 and 6 from the same quarter shows villas wrapped in scaffolding with finishing work going on…
  2. Later in the same film the villas are bare concrete frames, the earlier stage that matches the register's lower figure…

Nad Al Sheba Gardens | First look inside

Meraas

  1. In November 2025, a month before the register recorded Phase 2 as finished, Meraas filmed inside a completed villa: a…

See also

About this page

Last updated Nov 11, 2026 by the Vi.ki team. Page text CC BY-SA 4.0.

Edit History

Hotkeys

/
Jump to the search box
? or Ctrl + /
Open this list
Esc
Close this list, the photo viewer, or the account menu

Video

Space or K
Play or pause
← →
Back or forward 5 seconds
J L
Back or forward 10 seconds
0 to 9
Go to 0% to 90% of the video
, .
Previous or next frame, while paused
M
Mute or unmute
C
Captions on or off
F
Full screen on or off
A D
Previous or next moment

Photo viewer

← → or A D
Previous or next photo
↑ ↓ or W S
Previous or next photo
Home End
First or last photo
I
Show or hide the photo's info
Z
Clickless on or off: a pointer over a thumbnail shows it
N
Compare with the last photo: back to the one shown before this, and N again comes back
Q
Move the thumbnails to the next edge: top, bottom, left and round
, or Ctrl + ,
Open or close the viewer's settings
V
Clickless pan: a zoomed photo follows the pointer, rather than being dragged
Shift
Browse on or off
B
Show or hide the button bar
T
Show or hide the thumbnails
1
100% zoom on or off
0
Rate the photo as no opinion; again takes the answer back
+ -
Rate the photo a step higher or lower
F
Full screen: the photo alone. F again puts everything back.
Back to top